Project Portal - E2W Bundle 3
Authorised Access Only

Command Centre

E2W Bundle 3 - Rumbek-Ri Yubu - 529.8 km - 20 May 2026

Live

Command Centre

E2W Fiber Rollout Β· Bundle 3 Β· Rumbek <> Wau <> Ri Yubu Β· Overall progress: 55.97%

Overall OSP Progress
55.97%
Rumbek–Wau–Ri Yubu
Bundle 3
Rumbek <> Wau
~78%
231 km Β· Seg 1 leading
Advancing
Wau <> Ri Yubu
~32%
300 km Β· Seg 2
In progress
Inventory Gaps
5
Items with shortfalls
Action needed
Trenching Total
60.7%
322,505 / 531,240 m
HDPE Ducting
33.9%
360,000 / 1,062,480 m
Backfilling
34.0%
180,442 / 531,240 m
Fiber (FOC)
10.1%
58,250 / 579,650 m installed

Overall activity progress β€” both segments

Seg 1 Rumbek–Wau Seg 2 Wau–Ri Yubu

Progress breakdown

RoW Acquisition100%
Survey & Design100%
Trenching60.7%
HDPE Ducting33.9%
Backfilling34.0%
Fiber (FOC)10.1%

Daily trenching output β€” May 2026

Activity feed

Seg 1 Trenching β€” 10,800 m logged on 12 May. Highest single-day output.

12 May Β· Site Supervisor

FOC Installation β€” 58,250 m fiber pulled to date. Rumbek–Wau seg only.

Cumulative Β· Fiber Team

Inventory shortfall β€” HDPE 32mm: 505,300 m variance. Escalation required.

23 Apr Β· Procurement

HDPE Duct 110mm β€” 22,190 m requested, 0 received. Full shortfall unresolved.

23 Apr Β· Monicah

Seg 2 HDPE β€” 0 m ducting on Wau–Ri Yubu. Crew focussed on trenching.

Ongoing Β· PM

RoW & Survey β€” Both segments 100% complete. Full route cleared.

Completed Β· Survey Team

Progress & Workloads

Activity breakdown Β· targets vs executed Β· Both segments

Overall Seg 1
~78%
Rumbek–Wau Β· 231 km
Trenching
98.98%
227,945 / 230,290 m
HDPE 32mm
78.36%
361,216 / 460,980 m

Target vs Executed β€” Seg 1

Activity completion

Trenching98.98%
HDPE Duct Ξ¦32mm78.36%
Backfilling77.76%
HDPE Duct Ξ¦110mm20.3%
FoC Pulling23.66%
Bridge Attachment0%
FoC Splicing0%

Full Milestone Detail β€” Seg 1

#MilestoneUoMTargetExecutedVariance%Status
1Trenchingm230,290227,945+2,34598.98%On Track
2HDPE Duct Ξ¦32mmm460,980361,216-99,76478.36%Behind
3Backfillingm230,290179,068-51,22277.76%Behind
4HDPE Duct Ξ¦110mmm7,8301,593-6,23720.3%Behind
5FoC Pulling (UG)m246,15058,250-187,90023.66%Behind
6Bridge Attachmentm4500-4500%Not Started
7Concrete Envelopem11,8600-11,8600%Not Started
8Manhole InstallationPcs740-740%Not Started
9Handhole InstallationPcs780-780%Not Started
10Micro Tunnelingm1200-1200%Not Started
11Road Marker PostsPcs1520-1520%Not Started
12FoC SplicingBatch5,7600-5,7600%Not Started
13ODF PreconnectorizedPcs80-80%Not Started

Daily Progress

Field trenching records Β· Both segments Β· May 2026

Peak Day (May)
10,800m
12 May 2026
May Total
98,400m
20 working days recorded
Daily Average
4,920m
May 2026
Target/Day
6,000m
Combined both segments

Daily Log β€” May 2026

DateSeg 1 Trench (m)Seg 2 Trench (m)Total (m)vs TargetNoteEdit
01 May3,2001,8005,000β–² +200β€”
02 May2,8001,6004,400β–Ό -600Equipment maintenance
05 May3,6002,1005,700β–² +700β€”
06 May3,4001,9005,300β–² +300β€”
07 May4,2002,4006,600β–² +600β€”
08 May3,8002,2006,000β–² 0β€”
09 May4,1002,3006,400β–² +400β€”
12 May6,8004,00010,800β–² +4,800Peak day β€” all crews deployed
13 May4,5002,6007,100β–² +1,100β€”
14 May4,2002,4006,600β–² +600β€”
15 May3,9002,1006,000β–² 0β€”
16 May3,6001,8005,400β–Ό -600Rain delay
19 May4,8002,7007,500β–² +1,500β€”
20 May5,2003,0008,200β–² +2,200Strong finish

Full project daily output β€” Feb to May 2026

Monthly totals β€” Trenching (m)

Workloads by Segment

Milestone targets, executed values and variances

Seg 1 β€” Workload vs Target

Segment 1 Activities

#ActivityUoMTargetExecutedVariance%Edit

Risk Register

Active project risks - E2W Bundle 3

Critical
0
High
0
Medium
0

Full Risk Register

RefRiskLikelihoodImpactRatingMitigationOwnerStatusEdit

Customer Materials

Bayobab RTL/001/2026 β€” Material reconciliation as at 20 May 2026

Items Tracked
10
RTL/001/2026
Shortfalls
4
Items below requested
Fully Received
3
Items at 100%
HDPE Balance
505 km
32mm outstanding

Material Reconciliation β€” RTL/001/2026

MaterialUnitRequestedReceivedInstalledBalanceVarianceStatusEdit

Material comparison β€” Requested vs Received vs Installed

Internal Inventory

Ryatel equipment & consumable stock Β· 20 May 2026

Equipment Register

ItemTotal StockIn UseAvailableVarianceConditionStatus

Reports

E2W Bundle 3 β€” Rumbek-Wau-Ri Yubu Β· 529.8 km

Weekly Reports
3
Monthly Reports
3
Pending
1

Weekly Progress Reports

ReportPeriodSubmittedAuthorStatusDownload
Weekly Report W2013–17 May 202619 May 2026Project ManagerSubmitted
Weekly Report W1906–10 May 202612 May 2026Project ManagerSubmitted
Weekly Report W1829 Apr–03 May 202605 May 2026Project ManagerSubmitted

Monthly Progress Reports

ReportPeriodSubmittedAuthorStatusDownload
Monthly Report β€” May 2026May 202601 Jun 2026Project ManagerPending
Monthly Report β€” April 2026April 202601 May 2026Project ManagerSubmitted
Monthly Report β€” March 2026March 202601 Apr 2026Project ManagerSubmitted

Quality Alerts

NCR register and site quality issues

Open NCRs
0
In Review
0
Closed
0

NCR Register

RefDescriptionSegmentDateSeverityStatusEdit